1. Technical safety measures work at heights and with the necessary materials to be included in the project construction organization design.

2. Units responsible for construction project work at heights should be responsible for security technology and establish appropriate accountability. Before construction, safety and technical education should be one level and tests, and implement all safety measures and personal protective equipment technology, the implementation should not be conducted without the construction.

3. High job security signs, tools, instruments, electrical facilities and all equipment must be checked before construction to confirm its integrity, before being put into use.

4. Workers climbing and suspension height and erection of high security facilities, operations personnel, must be professional and technical training and professional examinations, certificates, and must periodically for physical examination.

5. Construction work on the safety of high technology facilities found to be defective and risks must be solved in time; risk of personal safety, and must cease operations.

6. Construction of all workplace objects could fall, should be removed or to be fixed first.

height of materials used in the operation should be stacked smooth, without prejudice to the movement and handling. Tools should be readily to release the tool kit; operating in the corridor, access panels and climbing equipment should be cleaned at any time; remove excess material under the object and should be cleared up and waste away, not indiscriminate home or down discarded. Prohibited objects thrown pass.

7. Rain and snow to a high place must be taken to secure non-slip, cold and freezing measures. Where water, ice, cream should be promptly removed. Operation of the high-rise building heights, lightning protection should be set in advance. In case of 6 or more strong winds, fog and other inclement weather, climbing and outdoor shall not be suspended at heights,Bailey UGG boots, storms and typhoons, the response to high operational safety to be checked one by one, found loose, deformation,UGG boots, damage or loss and other phenomena should be repaired immediately improved.

8. Necessary for operation, temporary removal or changes in security facilities, must be agreed by the person in charge of construction, and take the appropriate and reliable measures, operations immediately after recovery.

9. Erection and dismantling of protective shed, the warning area should be located, and should send someone to care. Up and down at the same time prohibited removed.

10. High job security force facilities in the main bar,UGG boots clearance, mechanical calculation formula for the normal structural mechanics, strength and deflection calculated according to existing norms, but the steel members in bending strength calculation does not take into account plasticity, construction should comply with the corresponding norms on requirements

high-altitude fall accident prevention and control

Posted :06-12-27 17:37:57 Read: 2931 Editor: Grey silver Source:

so-called high place, is more than 2m away from the base level (including 2m) may be operating on the height of fall. In the course of this operation caused the deaths and injuries due to fall, called the accident of falling from height. Such incidents have occurred in various industries, and Jian-sized, about 20% of all accidents.

1. the law of incidents of falling from height falling from height accidents

law refers to people engaged in a high place, the people when combined with related objects against the laws of objective things, the abnormal movement resulting from loss of control, occurred after a quantitative accumulation of the universality of disaster manifestations. Mastered the rules, we can effectively be prevented and controlled.

1.1 incidents of falling from height category

falling from height accidents following the accident about nine categories:

1.1.1 holes fall (reserved port openings, stairs, elevator, balcony fall mouth, etc.);

1.1.2 scaffolding fall;

1.1.3 fall vacant at heights;

1.1.4 asbestos and other light roof fall;

1.1.5 Demolition fall occurred;

1.1.6 climb during the fall;

1.1.7 job ladder fall;

1.1.8 roofing job fall;

1.1.9 Other operations falling height (tower on the pole, the equipment, structures, and trees,UGG bailey button, and other types of objects falling, etc.).

1.2 cause of the accident of falling from height